This was a DBO project of a water treatment plant to cater for a throughput of 18,000m³/day.
Works included full turnkey mechanical, electrical, instrumentation, control and automation, with civil works completed in a joint venture partnership with Bowen Construction.
Project Title
Utility
Client
Clare County Council
Type
DAF & Ultra Filtration & Disinfection
About the Project
Process included for:
- Chemical treatment
- Upfront flocculation
- DAF treatment followed by microfiltration for cryptosporidium removal
- Sludge treatment including thickening and
- Filter press dewatering.
Following successful commissioning and handover, the project transferred to a 20-year operation contract.