Ennis WTW
Co. Clare

This was a DBO project of a water treatment plant to cater for a throughput of 18,000m³/day. 

Works included full turnkey mechanical, electrical, instrumentation, control and automation, with civil works completed in a joint venture partnership with Bowen Construction.

Project Title

Utility

Client

Clare County Council

Type

DAF & Ultra Filtration & Disinfection

About the Project

Process included for:

  • Chemical treatment
  • Upfront flocculation
  • DAF treatment followed by microfiltration for cryptosporidium removal
  • Sludge treatment including thickening and
  • Filter press dewatering. 

Following successful commissioning and handover, the project transferred to a 20-year operation contract. 