Tullich WTW
Scotland

Project Title

Utility

Client

ESD/Scottish Water

Type

DAF/RGF/Mechanical DfMA Package

Rapid and efficient delivery of a new 12 MLD water treatment plant using off-site methods.

Tullich WTW supplies drinking water to the
communities in and around Oban in Argyll, Scotland.
The completed works takes raw water from Loch
Gleann A’Bhearraidh Reservoir and treats 7.2 million
litres of water a day through its filtration system.
Working at full capacity, it has the ability to process
11.8 million litres a day

Construction began on the site in Spring 2016 and
the site has been operational since December 2018.
It was delivered by Scottish Water’s delivery partner
ESD, and EPS were engaged (through its MEPS
joint venture with MWH Treatment) to deliver the
main treatment process units and interconnecting
infrastructure using off-site construction.

Project Cost
£ 1 M
EPS PACKAGE VALUE
£ 1 M

DEC 2018

COMPLETION DATE

PLANT CAPACITY
0 MLD

Project Background & Scope

Tullich Water Treatment Works is one of Scottish Water’s biggest ever investments in Argyll and Bute. The permanent population in Oban and the surrounding area of 12,000, more than doubles during the summer months to 40,000 due to the number of visiting tourists. The new water treatment works is providing cleaner, fresher, quality drinking water and will future proof supplies for more properties and development in the area for more than 20 years ahead.

The main project drivers were as follows:
– Ageing assets and old technology built 1970
– Changing and variable raw water quality
– Repeated THM challenges
– Vulnerability to cryptosporidium
– Need for greater supply resilience
– Negating use of ozone

The outline solution consisted of:
– New inlet pumping station
– Dissolved air flotation (DAF) plant
– Primary rapid gravity filters for solids
removal
– Secondary rapid gravity filters for manganese removal
– New motor control centres
– Chemical dosing
– Sludge treatment plant
– New administration building and workshop

Our Collaborative Approach

This is a major investment in our water infrastructure in the Oban area which will safeguard a robust and resilient water supply for many years to come.

DfMA Delivering Optimised Outcomes

By designing, manufacturing & testing the main process units, pipe racks, access platforms & other packages in the factory, EPS were able to de-risk and signifi cantly accelerate the on-site installation works at Tullich. DfMA principles were applied to over 80% of the overall MEICA scope of the project, including the following elements:
– Flocculation tanks
– Dissolved Air Flotation (DAF) Filters
– Primary Rapid Gravity Filters
– Secondary Manganese Filters
– Chemical Dosing Packages
– Inter-stage pipe racks including pipework, distribution
channels and electrical containment
– Access platforms and steelwork
– Pump skids
The elements produced & tested in the EPS factory were transported to the remote site location in Argyll & installed directly into their final positions on arrival. By eliminating on-site fabrication, hot work & the majority of working at height, EPS signifi cantly reduced safety, quality & weather-related risks & ensured the delivery of the project remained on-track

Scottish Water Treatment Works

See how the Tullich WwTW, Oban, Scotland is delivering cleaner, fresher water

In the very beginning, to get buy in from my operators, ESD could show them how to run it, how to maintain it in the virtual world which was fantastic. It meant they could visualise things before it was even built.

Delivery Partners

Proudly working alongside

Download our PDFs here:

Tullich
Case Study